    The first Zumwalt-class destroyer, the USS Zumwalt, the largest ever built for the US Navy, leaves the Kennebec River on Monday, December 7, 2015, in Phippsburg, Maine.

    $4.4 Billion USS Zumwalt Destroyer Towed From Panama Canal After Breakdown

    © AP Photo / Robert F. Bukaty
    Military & Intelligence
    Get short URL
    53808

    While passing through the lower half of the Panama Canal on Monday evening, a new Zumwalt-class destroyer broke down and had to be taken under tow to a berth, according to the US Third Navy Fleet in San Diego.

    The 610-foot, 16,000-ton vessel was towed to the Balboa Naval Station, a former US base. The ship cost $4.4 billion and is the most expensive destroyer built in Navy history. 

    Few details have been released regarding the incident, but the problem reportedly centers on heat exchangers housed in the vessel’s integrated power plant, which supplies electrical power to many of the ship’s key services including weapons, sensors and its propulsion plant. 

    The ship also sustained minor cosmetic damage after making contact with the canal’s lock wall.

    Defense News quoted a statement released on Monday by Third Fleet spokesman Commander Ryan Perry, saying, "Vice Adm. Nora Tyson, commander, US Third Fleet, has directed USS Zumwalt (DDG 1000) to remain at ex-Naval Station Rodman in Panama to address engineering issues that occurred while transiting the Panama Canal. 

    "The timeline for repairs is being determined now, in direct coordination with Naval Sea Systems and Naval Surface Forces. The schedule for the ship will remain flexible to enable testing and evaluation in order to ensure the ship's safe transit to her new homeport in San Diego."

    The Zumwalt was also sidelined with an engineering casualty in September, a month ahead of its commissioning ceremony in Baltimore. The Navy sent a statement to USNI News explaining the incident: 

    "The crew discovered the casualty after detecting a seawater leak in the propulsion motor drive lube oil auxiliary system for one of the ship’s shafts. The built-in redundancy of the ship’s propulsion plant allows this first-in-class ship to operate with multiple engine configurations. However, it was determined that the repairs should be completed in port prior to the ship transiting to sea."

    Following the vessel’s commissioning, more unspecified engineering issues arose, necessitating extra repair time and propulsion testing at Naval Station Mayport in Florida.

    Related:

    US Navy Satellite Begins Pre-Operational Testing After Rocky Ride Into Orbit
    US Navy's Warship USS Montgomery Completes Maiden Voyage
    United Shipbuilding Corporation to Deliver 12 Warships to Russian Navy in 2016
    UK Royal Navy 'Defenseless', With Less Firepower Than in the 19th Century
    US Navy Says No More $800,000 Ammo for New Zumwalt Destroyer
    Tags:
    repairs, USS Zumwalt, US Navy, Panama Canal
    Community standardsDiscussion
    Comment via FacebookComment via Sputnik