    A Tokyo Electric Power Co.'s (TEPCO) employee walks past storage tanks for contaminated water at the company's Fukushima Dai-ichi nuclear power plant in Okuma, Fukushima, Japan, on February 23, 2017

    Fukushima NPP’s Decontamination Costs Reach $22.7Bln

    © AFP 2017/ Tomohiro Ohsumi / POOL
    Asia & Pacific
    Get short URL
    621347

    The decontamination costs of the area surrounding the Fukushima nuclear power plant (NPP) are expected to grow due to the difficulty of the works that need to be carried out in hard-to-reach areas, according to the Japanese Environment Ministry.

    TOKYO (Sputnik) – Decontamination costs of the area surrounding the Fukushima nuclear power plant (NPP) reached some 2.6 trillion yen (approximately $22.7 billion) by the end of 2016 while further increase is likely, local media reported Friday, citing the Japanese Environment Ministry.

    The decontamination costs are expected to grow due to the difficulty of the works that need to be carried out in hard-to-reach areas, according to the Kyodo news agency.

    The full elimination of the accident’s consequences, including payment of compensation to the evacuees and the costs of the reactors’ dismantling will reach 21.5 trillion yen, compared to the earlier forecasts saying the costs would amount to 11 trillion yen, the Economy Ministry said in December.

    In late November, local media reported, citing the Economy Ministry’s data, that the costs of dismantling the Fukushima NPP’s reactors, expected to start in 2021 and last for 30 years, would amount to 8.2 trillion yen.

    The Fukushima disaster took place in March 2011, as an earthquake triggered a tsunami and hit the NPP, leading to the leakage of radioactive materials and the shutdown of the plant. People are still prohibited to live in the settlements, located near the NPP and the clean-up operations are expected to take about 40 years.

    Related:

    New Powerful 5.6 Earthquake Rocks Fukushima
    Record Radiation Aborts Robot Mission Inside Fukushima Reactor
    Tepco’s Toughest Robot Fails Inside Fukushima Reactor
    ‘Unimaginable’ – Understanding Radiation Levels Inside Fukushima Reactor
    Tags:
    Fukushima nuclear power plant, Japanese Environment Ministry
    Community standardsDiscussion
    Comment via FacebookComment via Sputnik
    • Сomment