RZD Completes Bujanovac-Bukarevac Railway Section Renovation in Serbia

© Wikipedia / Vesti onlineSerbian Railways Class 711
Serbian Railways Class 711 - Sputnik International
Subscribe
All rails were replaced as part of the effort, alongside upgrades of 13 railway crossings, two stations and the restoration of the overhead system and management and communications systems. After the renovation, trains will be able to circulate with a speed of up to 120 kph.

MOSCOW (Sputnik) — Russian Railways (RZD) has completed the renovation of Bujanovac-Bukarevac railway section in Serbia, the company said in a statement.

“The renovation project was carried out by RZD International, a Russian Railways subsidiary. The 14-kilometer Bujanovac-Bukarevac section in Serbia is the first out of three southern segments of the Pan-European Corridor X. The renovation was completed one month ahead of the deadline envisaged in the contract,” the statement reads.

Kievsky railway station in Moscow - Sputnik International
Russia
Russian Railways to Invest 8.4Bln to Rebuild Train Stations for 2018 World Cup
The company also pointed out that it was the first time that 36-hour technology breaks were used to carry out construction and installation work, so that the line did not come to a complete stop during renovation.

In addition, RZD International continues the renovation of Vinarci–Djordjevo line in Serbia, while work on Vranjska Banja–Ristovac is expected to be completed in the near future. The project to renovate the three southern sections of the Pan-European Corridor X is valued at more than $38 million. It is financed by a loan granted by the Russian government.